[单选题]

You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

(74)

A.Ahead of schedule

B.Behind schedule

C.On schedule

D.Having not enough information provided

参考答案与解析:

相关试题

The( )provides the project manager with

[单选题]The( )provides the project manager with the authority to apply organizational resources to project activities。A.project management planB.project charterC.project human resource planD.project stakeholders

  • 查看答案
  • The( )provides the project manager with

    [单选题]The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders

  • 查看答案
  • A project manager believes that modify

    [单选题] A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).(75)A.assign change tasks to project membersB.call a meeting of the configuration control boardC.chan

  • 查看答案
  • A project manager believes that modifyin

    [单选题]A. project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change

  • 查看答案
  • A project manager is called to an infor

    [单选题]A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager shoul

  • 查看答案
  • Project manager believes that modifyin

    [单选题] Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .(73) A. change the scope baselineB. contact the customer to determine if the change adds valueC. call a meeting of t

  • 查看答案
  • The()provides the project manager with t

    [单选题]The()provides the project manager with the authority to apply organizational resources to project activities.A . project management planB . contractC . project human resource planD . project charter

  • 查看答案
  • The(70)provides the project manager with

    [单选题]The(70)provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.contractC.project human resource planD.project charter

  • 查看答案
  • The ( ) provides the project manager with the authority to apply organizational resources to project

    [单选题]The ( ) provides the project manager with the authority to apply organizati

  • 查看答案
  • The ( ) provides the project manager with the authority to apply organizational resources to project

    [单选题]The ( ) provides the project manager with the authority to apply organizati

  • 查看答案
  •  You are a project manager for a small