[单选题]

Risk management allows the project manager and the project team not to(71).

A.eliminate most risks during the planning phase of the project

B.identify project risks

C.identify impacts of various risks

D.plan suitable responses

参考答案与解析:

相关试题

Risk management allows the project manag

[单选题]Risk management allows the project manager and the project team not to (71).A.eliminate most risks during the planning phase of the projectB.identify project risksC.identify impacts of various risksD.plan suitable responses

  • 查看答案
  • Risk management allows the project man

    [单选题] Risk management allows the project manager and the project team not to(71).(71)A.eliminate most risks during the planning phase of the projectB.identify project risksC.identify impacts of various risksD.plan suitable responses

  • 查看答案
  • The inputs of developing project manag

    [单选题] The inputs of developing project management plan do not include (72).(72)A. project charterB. stakeholder management strategyC. project scope statementD. outputs from planning processes

  • 查看答案
  • A project management technique that is

    [试题] A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activitie

  • 查看答案
  • ( )is a project management technique for

    [单选题]( )is a project management technique for measuring project performance and progress.It has the ability to combine measurements of the project management triangle: scope , time and costs.A.Critical path method(CPM)B.Earned value management(EVM)C.Net p

  • 查看答案
  • Project()Management is the Knowledge Are

    [单选题]Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.A . IntegrationB . TimeC . Planning

  • 查看答案
  • Project()Management is the Knowledge Are

    [单选题]Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning

  • 查看答案
  • In project management, a ( )is a list of

    [单选题]In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies a

  • 查看答案
  • Establishing a project management timeta

    [单选题]E.stablishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an elementA.relationshipsB.resourcesC.stakeholdersD.deliverables

  • 查看答案
  • Project (74) Management is the Knowled

    [单选题] Project (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.A.IntegrationB.TimeC.Plannin

  • 查看答案
  • Risk management allows the project manag