[单选题]

The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .(73)

A. measure, delay, record, distribute, analyze, and direct

B. plan, schedule, monitor, control, report, and forecast

C. promote, highlight, monitor, control, forecast, and report

D. emphasize, visualize, analyze, conceptualize, report, and record

参考答案与解析:

相关试题

The project requires more labor than ___

[单选题]The project requires more labor than ________.[A] has been put in[B] have been put in[C] being put in[D] to be put in

  • 查看答案
  • ()Fires may do more damage than the earthquakes.

    [问答题]()Fires may do more damage than the earthquakes.

  • 查看答案
  • Fires may do more damage than the earthquake.

    [问答题]Fires may do more damage than the earthquake.

  • 查看答案
  • Fires may do more damage than the earthquake.

    [问答题]Fires may do more damage than the earthquake.

  • 查看答案
  • Developing the project schedule is ofte

    [单选题]Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimat

  • 查看答案
  • Developing the project schedule is often

    [单选题]Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimat

  • 查看答案
  • Developing the project schedule is often

    [单选题]D.eveloping the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estima

  • 查看答案
  • Before a project schedule can be created

    [单选题]B.efore a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability for each resourceA.work breakdown structureB.baselineC.software requirements specificationD.plan

  • 查看答案
  • Project schedule management is made up

    [单选题] Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB. . a

  • 查看答案
  • A schedule is commonly used in projectplanning and project portfolio management. () on a schedule ma

    [单选题]A schedule is commonly used in projectplanning and project portfolio manage

  • 查看答案
  •  The project schedule is more than a do