[单选题]

A schedule is commonly used in projectplanning and project portfolio management. () on a schedule may be closelyrelated to the work breakdown structure(WBS)terminal elements, the statement ofwork, or a contract data requirements list.

A.Essences

B.Elements

C.Purposes

D.Issues

参考答案与解析:

相关试题

Project schedule management is made up

[单选题] Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB. . a

  • 查看答案
  • Project schedule management is made up o

    [单选题]Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A . activity duration estimating, schedule developing, activity resource estimatingB . activity reso

  • 查看答案
  • Developing the project schedule is ofte

    [单选题]Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimat

  • 查看答案
  • Developing the project schedule is often

    [单选题]Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimat

  • 查看答案
  • Developing the project schedule is often

    [单选题]D.eveloping the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estima

  • 查看答案
  • The project schedule is more than a do

    [单选题] The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team

  • 查看答案
  • Before a project schedule can be created

    [单选题]B.efore a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability for each resourceA.work breakdown structureB.baselineC.software requirements specificationD.plan

  • 查看答案
  • Your project is behind schedule due to c

    [单选题]Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().A . crashing the scheduleB . performing resource levelingC . conducting reverse resource

  • 查看答案
  • Tamlorn Mager, CFA, is an analyst at Pyallup Portfolio Management. CFA Institute recently notifiedMa

    [单选题]Tamlorn Mager, CFA, is an analyst at Pyallup Portfolio Management. CFA Inst

  • 查看答案
  • Tamlorn Mager, CFA, is an analyst at Pyallup Portfolio Management. CFA Institute recently notified M

    [单选题]Tamlorn Mager, CFA, is an analyst at Pyallup Portfolio Management. CFA Inst

  • 查看答案
  • A schedule is commonly used in projectplanning and project portfolio management. () on a schedule ma