[单选题]

The Estimate Activity Resource process is closely coordinated with the (73)process.

(73)

A. Estimate Costs

B. Sequence Activities

C. Plan Communications

D. Conduct Procurements

参考答案与解析:

相关试题

The Estimate Activity Resource process i

[单选题]The Estimate Activity Resource process is closely coordinated with the(73) process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements

  • 查看答案
  • The Estimate Activity Resource process i

    [单选题]The Estimate Activity Resource process is closely coordinated with the(73)process.A.Estimate CostsB.Sequence ActivitiesC.Plan CommunicationsD.Conduct Procurements

  • 查看答案
  • The Estimate Activity Resource process i

    [单选题]The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements

  • 查看答案
  • Estimate activity durations is the proce

    [单选题]E.stimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().A.expert judgmentB.analogous estimatingC.requiremen tstraceability matrixD

  • 查看答案
  • The process of()schedule activity durati

    [单选题]The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A . estimatingB . definingC . planningD . seq

  • 查看答案
  • On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.A

    [单选题]On some projects,especially ones of smaller scope,activity sequencing,activ

  • 查看答案
  • The process of (74) schedule activity du

    [单选题]The process of (74) schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A.definingB.estimatingC.planningD.sequenc

  • 查看答案
  • The process of(72)schedule activity dura

    [单选题]The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing

  • 查看答案
  • The process of ( ) schedule activity durations uses information on schedule activityscope of work, r

    [单选题]The process of ( ) schedule activity durations uses information on schedule

  • 查看答案
  • Changing an accounting estimate:

    [单选题]Changing an accounting estimate:A.Is reported prospectively.B.Requires rest

  • 查看答案
  •  The Estimate Activity Resource process