[单选题]

On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and ( ) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.project planning

B.time estimating

C.cost estimating

D.schedule development

参考答案与解析:

相关试题

On some projects, especially ones of s

[单选题] On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a rel

  • 查看答案
  • On some projects, especially ones of sma

    [单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and(70)are so tightly linked that they are viewed as a single process that can be performed by a person over a relati

  • 查看答案
  • On some projects, especially ones of sma

    [单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relati

  • 查看答案
  • On some projects,especially ones of smal

    [单选题]On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relativel

  • 查看答案
  • Estimating activity durations uses information on activity scope of ( ) , requiredresource types, es

    [单选题]Estimating activity durations uses information on activity scope of ( ) , r

  • 查看答案
  • The Estimate Activity Resource process

    [单选题] The Estimate Activity Resource process is closely coordinated with the (73)process.(73)A. Estimate CostsB. Sequence ActivitiesC. Plan CommunicationsD. Conduct Procurements

  • 查看答案
  • Estimating activity durations uses inf

    [单选题] Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.(74)A. milestoneB. baselineC. qualityD. work

  • 查看答案
  • Estimating schedule activity costs invol

    [单选题]E.stimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application

  • 查看答案
  • Estimating activity durations uses infor

    [单选题]Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.A . milestoneB . baselineC . qualityD . work

  • 查看答案
  • Estimating schedule activity costs invol

    [单选题,共用题干题] Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most applic

  • 查看答案
  • On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.A